Manhattan / Full gut renovation

Full Gut Renovation in Manhattan

A full gut is not a single demolition event. Corniel Construction coordinates existing-condition discovery, systems work, approvals, protection, procurement, and finish decisions.

The planning figure

Plan for 9–12 months total.

The company planning figure includes 3–5 months for design and pre-construction, 4–7 months for construction, and about 1 month for close-out with a Letter of Completion. A project-risk review helps surface scope and schedule issues before work begins.

01 / Design & pre-construction

3–5 months

Planning, approvals, filings, procurement, and site readiness.

02 / Construction planning

4–7 months

Active construction: 4–6 months (16–24 weeks) once permits are issued.

03 / Close-out

~1 month

Punch list, closeout documentation, and Letter of Completion. Final inspections are typically 1–2 weeks.

What changes behind the finish

Open the walls with a plan.

01

Strategic demolition

Protect building systems and structural integrity, follow NYC debris removal protocols, contain dust for neighboring units, and schedule debris removal per building guidelines.

02

Plumbing modernization

Replace galvanized or cast-iron lines with modern materials, add supply lines and waste stacks, relocate bathrooms or kitchens when feasible, plan for high-rise water pressure, and provide fixture shut-off valves.

03

Electrical overhaul

Coordinate panel upgrades, new wiring, dedicated circuits for major appliances, smart-home integration, and USB charging.

04

Custom carpentry & millwork

Use built-in storage for Manhattan’s limited square footage, custom cabinetry, closet systems, and pre-war restoration of picture rails, wainscoting, decorative moldings, window casings, door frames, crown molding, and baseboards.

ILLUSTRATIVE EXAMPLES

AI-generated illustration of pre-renovation planning materials and a room under considerationAI-generated illustration. Not a completed Corniel project.
AI-generated illustration. Not a completed Corniel project.

COMPLETED CORNIEL PROJECTS

Exposed plumbing infrastructure during a verified construction process
Verified Corniel Work — process documentationPlumbing infrastructure / process visual.
Bathroom pressure-test process visual during verified construction work
Verified Corniel Work — process documentationBathroom pressure-test / quality-control process visual.

What we manage

The surrounding work stays visible.

Wall-prep restoration detail during a verified construction process
Verified Corniel Work — process documentationWall-prep restoration detail near finish-quality review.

We help coordinate filings through licensed professionals when required.

Final approvals are determined by the building, board, or applicable agency.